Pre-Construction Preparation

  1. Site Clearing

    • Remove vegetation/obstacles with minimal ground disturbance

    • Maintain natural soil structure (avoid over-compaction)

  2. Material Inspection

    • Cell size: 400×400mm (typical for soft soils)

    • Sheet thickness: ≥1.2mm

    • Verify geocell specifications:

    • Prepare 600mm extended-length ground anchors

  3. Survey Layout

    • Establish control points with RTK GPS (±20mm accuracy)

Construction Sequence

1. Geocell Deployment

  • Laying Method:

    • Unroll parallel to traffic direction

    • Maintain 2-3% prestress tension

  • Surface Adaptation:

    • Allow 50-100mm vertical conformity to terrain

2. Anchoring System

  • Fixation Parameters:

    • Rebar stakes: Φ12mm @ 1.0m grid

    • Embedment depth: ≥0.6m in saturated soils

3. Infill Placement

  • Material Selection:

    • Graded aggregate (5-20mm) for base layer

    • Maximum particle size: ≤1/3 cell height

  • Compaction Protocol:

    • 150mm lifts with vibratory plate compactor

    • Target density: 92-95% Standard Proctor

4. Panel Connection

  • Junction Details:

    • Use ≥3 polymer connectors per lineal meter

    • Overlap seams with 200mm minimum extension

Critical Construction Considerations

1. Operational Limitations

  • Equipment Restrictions:

    • Ground pressure: <20kPa for tracked vehicles

    • Avoid rut formation >50mm depth

2. Weather Management

  • Work Window:

    • Precipitation >10mm/24hr

    • Soil moisture content >LL+10%

    • Prohibit operations when:

3. Quality Control Measures

  • Real-time Monitoring:

    • Laser scanning for surface evenness (<30mm deviation)

    • Nuclear density tests for infill compaction

Post-Construction Maintenance

1. Inspection Regimen

  • Frequency:

    • Weekly for first month

    • Monthly thereafter

  • Focus Areas:

    • Anchor integrity

    • Infill retention

2. Protection Measures

  • Access Control:

    • Install temporary fencing with 2m setback

  • Erosion Control:

    • Apply coconut fiber mats on exposed edges

3. Ecological Integration

  • Revegetation Protocol:

    • Hydroseed with 80g/m² native grass mix

    • Initial irrigation: 15L/m²/day for 30 days


Title"Geocell Stabilization of Waterlogged Soils: Engineering Protocols and Performance Verification"

Technical Specifications:
▸ Design Load Capacity: 50-150kPa (dependent on infill)
▸ Construction Rate: 200-400m²/day
▸ Service Life: 15-20 years in saturated conditions

Cost Analysis:

  • Material + Installation: $18-35/m²

  • Lifecycle Savings: 40% vs. stone column methods

Standards Compliance:
✔ ASTM D8265 - Geocell soft ground applications
✔ ISO 13426 - Connection strength testing
✔ BS 8006 - Reinforced soil structure design

CONTACT US

COMPANY:TAI'AN CITY RUIHENG BUILDING MATERIALS CO., LTD

Contact:Nickle Nie

Tel:008615866038408

Phone:008615866038408

Email:nickle@rhgeos.com

Add:NO.3566 LONGQUAN ROAD,TAI'AN HI-TECH ZONE,SHANDONG PROVINCE,CHINA